Construction Progress Photos October 2009 Wednesday, October 21, 2009 Share on Facebook
Wide Shot East Side of Building September 30, 2009
General Office South West Parking Lot September 25, 2009
New Electrical Room South West Lower Level September 25, 2009
West Side of Building Construction Area September 25, 2009
North East Side of Building September 25, 2009
Construction
to Date:
As part of Phase I construction the
following work has been completed:
Upgrades to various utility services (sewer, gas,
electrical).
Outside precast panel walls measuring 31’ X 5’ and
weighing 8,000 pounds each were removed.
Initial work on the foundation footings for the new
outside wall has begun.
New outside walls will be built during the 2009-10
season.
WHAT TO EXPECT ON YOUR NEXT VISIT TO THE ENMAX CENTRE Monday, October 05, 2009 Share on Facebook
General Information: The City of
Lethbridge ENMAX Centre expansion and renovation project started construction
in May 2009. The purpose of this project is to improve existing services and to
continue to meet and/or exceed the needs and expectations of our customers and
business partners.
The
improvements to the building will allow the facility to compete in the
increasingly competitive market place for the next 25 years. The building space
is currently 151,833 sq. ft., through this expansion an additional 40,809 sq.
ft will be added creating an overall total space of 192,642 sq. ft.This project is scheduled to be completed
over a 3 year period from 2009-2012. During these 3 years the building will be
open to the public and fully operational from October-April of each
construction year.
Construction to Date: As part of
Phase I construction the following work has been completed:
• Upgrades
to various utility services (sewer, gas, electrical). • Outside
precast panel walls measuring 31’ X 5’ and weighing 8,000 pounds each were
removed. • Initial
work on the foundation footings for the new outside wall has begun. • New
outside walls will be built during the 2009-10 event season.
General Offices: ENMAX
Centre General Office & Hurricanes Office have been relocated for the
duration of the 3 year enhancement project. Our offices are now located in
trailers on the West side of our building in the South end of the parking lot. CLICK HERE FOR MAP
All contact
information, phone numbers and emails will remain the same for the General
Office, Hurricanes Office and Ticket Centre.
Ticket Centre: The Ticket
Centre located at the ENMAX Centre will be operating in its original location
under its normal hours until May 2010.
Washrooms: The
washrooms in our facility will not be affected for the 2009-2010 Season.
Seating: Due to the
elimination of various exit doors the building occupant capacity has been
reduced by 1,000 available seats for hockey and other events. Seating capacity
for hockey games will be 4,000 seats and concerts 5,600 available seats during
this Phase of the construction.
Food & Beverage: All
concessions at the facility will be fully operational through this season. The
Mini Melts concession stand previously located on the SW corner of the
concourse will not be operating for this season.
Hurricane Souvenir Store: The
Souvenir store will be temporarily located on the SW corner of the concourse.
(Previously the Mini Melts location)
Information Centre: Customers
who need assistance during Hockey Games or Special Events are encouraged to
visit the Information Centre which will be located in the old Hurricanes
Souvenir Shop on the North West end of the building for the 2009-2010 Season.
Parking & Football Field: Parking in
the West Lot has been reorganized to accommodate ENMAX Centre and Hurricanes
staff all other parking at the facility remains the same for public use at
events.
The
football field located on the East side of the building is presently housing
construction equipment for the expansion and will operate in the future as an
additional parking lot.
Luxury Suites: Two of our
Luxury Box Suites at the North end of the building have been vacated and will
be demolished in preparation for the addition of 16 new suites.
Fire & Safety: Fire
Marshals will be on site to assist in directing patrons to the nearest exits
and out of the building in the event of an emergency evacuation. CLICK HERE FOR MAP
Construction Photos Progress September 2009 Thursday, September 10, 2009 Share on Facebook
September 1, 2009 West Side of Building
July 21, 2009 East Side of Building
July 8, 2009 Precast Removal East Side of Building
June 5, 2009 East Side of Building
June 5, 2009 West Side of Building
GROUNDBREAKING CEREMONY PROVINCE ANNOUNCES $17.8 FUNDING FOR PROJECT Tuesday, July 28, 2009 Share on Facebook
The Puck Drop In photo from left to right: Mayor Robert Tarleck, Shaun Haney, Director, Lethbridge Hurricanes, Greg Weadick, MLA Lethbridge West, Bridget Pastoor, MLA Lethbridge East, The Hon. Ray Danyluk, Minister Municipal Affairs
FOR IMMEDIATE RELEASE
July 28, 2009
LETHBRIDGE - Today, the Hon. Ray Danyluk, Minister of Municipal
Affairs, announced that the Province
of Alberta is providing
$17.8 million in funding from its Municipal Sustainability Initiative (MSI) to
support the completion of the ENMAX Centre Expansion project.
“Over the years, the ENMAX
Centre has been a hub of activity for citizens in communities across southern Alberta. I am pleased
that the Government of Alberta can support an expansion project that brings
communities together,” said Danyluk. “Throughout the province, MSI funding is
having a real impact, by enabling local councils, like Lethbridge, to make decisions that meet the
needs of their citizens.”
“The provincial funding
announced today is in addition to the $3.7 million in funding from the
province’s Major Community Facilities Program (MCFP) announced last December,”
says Greg Weadick, MLA Lethbridge West.“The MCFP funding was based in large part on community support. Clearly
the residents of Lethbridge
and surrounding communities appreciate the value of having a facility of this
caliber in the community.”
“Partnerships have made this
$33.7 million dollar project possible,” says Mayor Robert Tarleck. “The City is
grateful to the Province of Alberta for contributing almost two-thirds of the
funding for an expansion project that will see about 41,000 sq. ft. of space and
major new amenities added to the building.”
In addition to the funding
from the Province, the City of Lethbridge will contribute $4.3 million and, in
partnership with the Lethbridge Hurricanes, support a loan of $7.9 million
which will be paid back through a combination of new facility revenues sources,
and a contribution from the Hurricanes of $2.5 million over 15 years.
Demolition of a portion of
the existing structure has begun, and the building is closed for renovations
over the summer. Construction will be scheduled over a three-year period, with
major construction phases scheduled during the summer months.
“During the height of the
entertainment season the shows will go on,” says Tarleck.“The expansion is scheduled for completion in
the late summer of 2012.Once the
project is complete, the upgraded facility will continue to bring high quality
entertainment to the city for another 35 years.”
For more Information call
Lori Skriver, Marketing Manager at 320-4245 or email lskriver@lethbridge.ca
ENMAX Centre General Office & Hurricanes Office Relocated Wednesday, June 17, 2009 Share on Facebook
Relocated Offices Map
IMPORTANT NOTICE: ENMAX Centre General Office & Hurricanes Office have been relocated for the duration of the 3 year enhancement project.
Our offices are now located in trailers on the West side of our building in the South end of the parking lot near the Club Seat Holders parking stalls. (See Map above)
The Ticket Centre at the ENMAX Centre is not being relocated at this time and will be operating under its normal hours throughout the Enhancement Project.Also, contact information, phone numbers and emails will remain the same for the General Office, Hurricanes Office and Ticket Centre.
Check this section on a regular basis to get all the latest news and updates regarding the Building Enhancement beginning June/July 2009 at ENMAX Centre!